Section titled “How to Change the Status of a Cycle Count”Cycle Counts move through controlled statuses to protect inventory accuracy.
Status Workflow Overview
Section titled “Status Workflow Overview”| Current Status | Next Action | System Rule / What Happens |
|---|---|---|
| Draft | Move to Processing | Audit is activated and sent to the floor. Inventory Freeze is applied to all items in scope. |
| Processing | Move to Completed | Only allowed when all items have been counted. Inventory Freeze is lifted. |
| Processing | Move to Cancelled | Audit is aborted; Inventory Freeze is lifted immediately. |
warning: Inventory Freeze While a Cycle Count is in Processing, UniCMMS blocks manual Stock Operations (Stock In / Stock Out / Consume / Receive) for items in the audit.
Step 1 – Access the Cycle Counts List
Section titled “Step 1 – Access the Cycle Counts List”- From the main sidebar, expand Parts & Supplies.
- Click Cycle Counts and ensure you are on the List tab.
Step 2 – Check the Current Status
Section titled “Step 2 – Check the Current Status”- Locate your audit in the list.
- Note its current value in the Status column (e.g.
DraftorProcessing).
Step 3 – Open the Action Menu
Section titled “Step 3 – Open the Action Menu”- In the same row, click the More (⋯) icon in the far‑right column.
Step 4 – Advance the Audit
Section titled “Step 4 – Advance the Audit”From the dropdown menu, select the next logical step:
- If the status is Draft, choose Processing to activate the count and apply the Inventory Freeze.
- If the status is Processing and all parts have been counted, choose Completed.
- If the status is Processing but the audit must be abandoned, choose Cancelled to lift the freeze without completing the count.